|

Page
1 of 3
As the first round of nuclear plant decommissionings begin, and
a decade after the end of the cold war, opportunities exist for
companies with the expertise necessary for decontaminating and
decommissioning nuclear facilities, including both commercial
nuclear reactors and the legacy from the DOE Weapons Complex.
Framatome Technologies' years of involvement in nuclear energy
make the company particularly suited to playing a role in this
emerging business.
The FTI Decontamination & Decommissioning group has performed
work or is in the pre-deployment phase for performing work at
commercial reactors being decommissioned. FTI's contracted work
includes segmenting reactor vessel internals, cutting loose major
components, fuel inspection and materials characterization.
Maine Yankee
Internals Segmentation
This past spring FTI was awarded a contract to segment the reactor
vessel internals of the decommissioned Maine Yankee plant, the
group's largest project to date.
"In this highly technical aspect of the plant's decommissioning,
FTI will segment the reactor vessel internals using a combination
of abrasive waterjet and mechanical cutting. Then we will package
the segmented internals and secondary cutting waste for disposal,"
said FTI's Bob Twilley, Manager of D&D. The segmentation will
be performed remotely inside the refueling cavity, under water
to minimize personnel radiation exposure.
The segmenting of internals at Maine Yankee is scheduled to begin
this spring and take approximately eight months on site. This
type of work is unlike FTI's traditional outage work where schedules
are driven by the customer's desire to resume electricity production
as quickly as possible. FTI has been at work on pre-deployment
preparations for six months, including design activities, qualifications
testing and placing orders for required major equipment.
FTI has turnkey responsibility for this technically challenging
step of the Maine Yankee plant D&D, as a subcontractor to Stone
and Webster Construction Company (S&W), which has overall responsibility
for the Maine Yankee D&D.
FTI has supported S&W in the development of a unique reactor
pressure vessel packaging and internals segmentation plan for
Maine Yankee. Based on this plan, FTI will apply innovative abrasive
waterjet cutting, segmentation sequencing and waste processing
techniques in order to meet the challenges presented at Maine
Yankee.
"The challenges at Maine Yankee result from limited available
workspace in the refueling cavity, the geometry of the internals,
the radioactivity of the materials and the need to minimize both
radiological dose and secondary waste disposal volume," said Sue
Coleman, FTI's Project Engineer for the project.
FTI has also developed a process to contain and collect the
waste resulting from the cutting, and is responsible for maintaining
water clarity and refueling cavity cleanliness during and after
the internals segmentation process.
"We are excited about this major project as Framatome Technologies'
continues its movement into the D&D services arena," said FTI
President Lyle Bohn. "The award of this technically challenging
project shows the industry recognizes our expertise in this area."
   
|