|
Ah…spring
outage time. At the Davis Besse (DB) plant in Oak Harbor, Ohio,
the words “spring cleaning” took on new meaning. Secondary-side
chemical cleaning of the plant’s two once-through steam generators
(OTSGs) was in full swing, and life was good.
“It was the
smoothest SG cleaning operation I’ve ever been involved with,”
said Ron King, Supervisor, Application Engineering and Chemical
Cleaning Task Leader for Framatome Technologies. “Everyone cooperated,
and the plant team worked well with our team members to get the
job completed in record time.”
“In fact,
the job was completed 42 hours ahead of schedule,” King said.
“It was a
good job,” said Richard Chesko, Sr. Engineer - Projects at DB.
“The Framatome team, and our personnel all deserve an ‘Atta Boy,’”
he declared. “Due to previous replacement of our main feedwater
nozzles and this being the first time our generators were cleaned,
we all expected improved operating levels. When the unit started
back up, we were extraordinarily pleased to find that operating
levels were even better than original startup levels.”
The SGs at
Davis Besse have been in operation since 1977 without a cleaning
or replacement. Once-through steam generators are unusual in the
industry. These workhorses of nuclear power are approximately
68 feet high and 13 feet in diameter, so cleaning one requires
miles of hoses, tons of chemicals and numerous holding tanks –
so many, in fact, it is termed a tank farm. All this equipment
is moved to the site for the operation, and then dismantled and
sent to the next job.
During the
Davis Besse outage, Framatome Technologies used the Electric Power
Research Institute/SG Owners Group (EPRI/SGOG) low-temperature
method to remove magnetite deposit buildup in the OTSGs that accumulated
during years of service. The deposits had built up in the broached
openings of the tube-support plates, and in turn were causing
increased pressure drop on the secondary side. Had the deposit
buildup not been removed, power output would eventually have had
to be reduced, which is an extremely undesirable condition in
today’s competitive marketplace.
More than
5,000 pounds of deposits were removed during the cleaning. SG
1 was cleaned in approximately 100 hours, removing 2,600 pounds
of deposits. SG 2 took approximately 120 hours and 2,500 pounds
of deposit were removed. Following the chemical cleaning, an additional
900 pounds were removed by sludge lancing. After the cleaning
operations were complete, eddy-current testing and visual inspections
clearly demonstrated that the SGs were essentially 100 percent
free of debris or deposits of any kind.
Other OTSGs
have had similar results – the generators FTI cleaned at two other
sites produced between 6000 and 9000 pounds of deposits. The average
OTSG deposit removal is 7,000 pounds. The Westinghouse recirculating
steam generator averages 14,000 pounds. Some chemical cleanings
that FTI has performed have removed over 35,000 pounds of deposits.
Radiation
dose levels for the Davis Besse chemical cleaning were the lowest
ever for FTI for this type of chemical cleaning, due in part to
the timesaving on various steps of the operation.
Waste
Processing
Waste
processing at Davis Besse also took five fewer days than anticipated.
FTI performed its standard waste-reduction of the liquid waste
generated by the cleaning process. More than 83,000 gallons of
waste were processed through a four-pass, forced-circulation evaporator
to produce approximately 71,000 gallons of distillate solution
that was released back to the plant. An additional 12,000 gallons
of concentrated solution was shipped off-site to a low-level radioactive-waste
treatment facility for further treatment and subsequent shipment
for disposal.
“All in all,
we were very pleased with the cooperation between the two teams,
the smoothness of operations, and the final results,” said King.
click
to Learn
more of Framatome's Chemistry Cleaning Services
|